To illustrate how cost variance analysis works

To illustrate how cost variance analysis works - developed:...

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
To illustrate how cost variance analysis works, assume you are the plant manager for Bases, Inc., a  company that makes a set of soft bases for playing baseball in gymnasiums. The budget assumes  150,000 sets of bases will be produced annually. The following standard cost per set of bases was 
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: developed: Quantity per set Cost Cost per set Direct Materials 4.5 feet $1.10 $ 4.95 Direct Labor .5 hour $9 per hour 4.50 Manufacturing Overhead .5 hour $1.30 per .65 Total Cost per Unit $10.10...