Year Actual Cost Incurred Estimated Cost to Complete % Completed Project Billings Collections on Billings 2010 $7,600,000.00 $18,400,000.00 30% $9,500,000.00 $9,000,000.00 2011 9,700,000.00
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: 8,900,000.00 80% 11,500,000.00 10,300,000.00 2012 8,800,000.00 - 100% 9,000,000.00 10,700,000.00 Total $26,100,000.00 $27,300,000.00 $30,000,000.00 $30,000,000.00...