Question: 1
How does R3LOAD handle restart situations based on the task file content?
There are 2 correct answers to this question.
Response:
A.
If the status is „err“ for a data import task, R3LOAD will drop the table to restart the import.
B.
If the status is „err“ for a create primary key task, R3LOAD will delete data and recreate the primary
key to restart the import.
C.
If a status is „err“ for a create index task, R3LOAD will drop the index and recreate it to restart the
import.
D.
If the status is „err“ for a create table task, R3LOAD will drop and recreate the table to restart the
import.
Answer: B,D
Question: 2
What can you do with the Software Provisioning Manager?