CE 167: Engineering and Project Management Professor William Ibbs Fall 2011 Homework 8: Resource Leveling, Crashing, and Earned Value Analysis 25 Points Due: Dec. 6th, 2011 1. [8 points] Given the following table of activities: Activity Duration Predecessors Resources A 4 --- 6 B 8 A 3 C 4 A 5 D 5 B 1 E 3 D 3 F 6 C,D 5 G 4 C 4 H 9 F 2 I 6 E,G,H 5 a. Draw the network using the AON convention, and calculate the ES, EF, LS, LF for every activity. Identify the critical path and it’s duration. b. Draw the resource diagram for the early start schedule