CE 167: Engineering and Project Management Professor William Ibbs Fall 2011 Homework 8: Resource Leveling, Crashing, and Earned Value Analysis 25 Points Due: Dec. 6th, 2011 1. [8 points] Given the following table of activities: Activity Duration Predecessors Resources A 4 --- 6 B 8 A 3 C 4 A 5 D 5 B 1 E 3 D 3 F 6 C,D 5 G 4 C 4 H 9 F 2 I 6 E,G,H 5 a. Draw the network using the AON convention, and calculate the ES, EF, LS, LF for every activity. Identify the critical path and it’s duration. b. Draw the resource diagram for the early start schedule
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
What is the average number of resources committed each day? =(6*3+8*5+3*4+1*5+12*3+9+5*2+2*9+6*5)/38 = 4.7 d. Level the resources given that the maximum number of resources available on any given day is 6. Draw a new resource diagram and in a separate table indicate the new start and finish dates for each activity. Do not change the end date of the project. Start
Background image of page 2
Image of page 3
This is the end of the preview. Sign up to access the rest of the document.

Page1 / 5

CE167_ Fall_2011_HW8_Solutions - CE 167: Engineering and...

This preview shows document pages 1 - 3. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online