MGT 302 Individual Assignment 3

MGT 302 Individual - Crash Cost 1st Crash=Activity A By 1 Day $1,000 2nd Crash=Activity C By 1 Day $1,200 3rd Crash=Activity D By 1 Day $1,750 4th

Info iconThis preview shows pages 1–4. Sign up to view the full content.

View Full Document Right Arrow Icon
Problem 1: A Activity Time Activities 1 2 3 4 5 6 7 8 A B C D E F G H Problem 1: B Activity Time 1 2 3 4 5 6 7 8 A B C D E F G H
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Problem 1: C Start A (2) B(3) C(1) D (2) F (5) H(3) E(2) G (4) END
Background image of page 2
Problem 1: D,E,F,G ES EF LS LF Total Slack Free Slack A 0 2 0 2 0 0 B 0 3 1 4 1 1 C 0 1 1 2 1 0 D 2 4 2 4 0 0 E 1 3 2 4 1 1 F 2 7 3 8 1 1 G 4 8 4 8 0 0 H 1 4 5 8 4 4 Problem 1: H There would be no effect on the total project if Activity B was delayed by 1 day because Activity B has free slack of 1 day.
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Background image of page 4
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: Crash Cost 1st Crash=Activity A By 1 Day $1,000 2nd Crash=Activity C By 1 Day $1,200 3rd Crash=Activity D By 1 Day $1,750 4th Crash=Activity F By 1 Day $2,000 Starting Critical Path= ACDFG Ending Critical Paths= ACDFG, ABDFG...
View Full Document

This note was uploaded on 01/31/2012 for the course MGT 302 taught by Professor Baker during the Spring '09 term at Miami University.

Page1 / 4

MGT 302 Individual - Crash Cost 1st Crash=Activity A By 1 Day $1,000 2nd Crash=Activity C By 1 Day $1,200 3rd Crash=Activity D By 1 Day $1,750 4th