OM2 -C18 OM2 Chapter 18: Project Management-problem solutions Problems, Activities, and Discussions (4) Construct a project network for the activities listed below. Do not attempt to perform any further analysis. Immediate Activity Predecessor A B C A D A,B E C,D F C,D G E H F 1
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
OM2-C18 (5) Rozales Manufacturing Co. is plarming to install a new flexible manufacturing system. The activities that must be performed, their immediate predecessors, and estimated activity times are shown below. Draw the project network and find the critical path computing early and late start days, early and late finish days, and activity slack. Estimated Immediate Activity Time Activity Description Predecessors (days) A Analyze current performance 3 B Identify goals A 2 C Conduct study of existing operation A 6 D Define new system capabilities B 7 E Study existing technologies B 2 F Determine specifications D 7 G Conduct equipment analyses C,F 10 H Identify implementation activities C 3 I Determine organizational impacts H 4 J Prepare report E, G, I K Establish audit procedure H o 3 sr=IO sr= 15 The table below summarizes the dates and slack for each activity. 2
Background image of page 2
OM2 - C18 Activity Immediate Predecessor Time (days) Earliest Start Earliest Finish Latest Start Latest Finish Slack A --- 3 0 3 0 3 0 B A 2 3 5 3 5 0 C A 6 3 9 13 19 10 D B 7 5 12 5 12 0 E B 2 5 7 27 29 22 F D 7 12 19 12 19 0 G C,F 10 19 29 19 29 0 H C 3 9 12 22 25 13 I H 4 12 16 25 29 13 J E,G,I 2 29 31 29 31 0 K H 3 12 15 28 31 16 Critical path is A-B-D-F-G-J with a final project completion time of 31 days. 3
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
OM2 - C18 (6) A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below. Immediate
Background image of page 4
Image of page 5
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 03/15/2012 for the course BUS-P 301 taught by Professor Ippolito during the Spring '12 term at IUPUI.

Page1 / 10

Chapter 18 solutions 4-8 - OM2 - C18 OM2 Chapter 18: Project

This preview shows document pages 1 - 5. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online