Homework 4 Due: Oct 9th 2008 1. Problem #4 in Eric Denardo’s book, on page 105. 2. Problem #5 in Eric Denardo’s book, on page 106. 3. Consider a production planning problem for the next 5 months. The demands for the 5 months are d 1 = 2 ,d 2 = 4 ,d 3 = 2 ,d 4 = 2 and d 5 = 3. If the decision for a month is to produce, then there
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: is a setup cost of $4,000 and a unit production cost of $1,000. There is a unit holding cost of $300. The initial inventory level is 0 and no backlog is allowed. Use Wagner-Within algorithm to nd the optimal production plan. 1...