Hesham A. Aziz 1 Project time Management Program Evaluation and Review Technique “PERT” Dr. Hesham A. Aziz
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Hesham A. Aziz 2 PERT is a probabilistic approach to project planning. It uses estimates of activity durations that are known (reasonably accurately). PERT is event oriented as it works on calculating the probability of events being completed within a given time. Assumes each activity duration has a range that statistically follows a beta distribution . Program Evaluation and Review Technique (PERT)
Background image of page 2
Hesham A. Aziz 3 The basic steps involved in a PERT analysis are to: assign three durations to each activity ( optimistic, most likely and pessimistic); calculate activity mean duration and standard deviation; calculate forward and backward pass values; identify those activities with no spare time contained within the duration (critical path); calculate project mean duration and standard deviation; identify target completion date and calculate variance about target;
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Hesham A. Aziz 4 PERT—PROGRAM EVALUATION REVIEW PERT—PROGRAM EVALUATION REVIEW TECHNIQUE TECHNIQUE PERT uses three time estimates for each activity:
Background image of page 4
Image of page 5
This is the end of the preview. Sign up to access the rest of the document.

Page1 / 21

12- PERT - Project time Management Program Evaluation and...

This preview shows document pages 1 - 5. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online