Copy of - 24 9 12 14 16 Landscaping 3 15 17 PLANT READINESS PHASE(Summary 18 Plant Personnel Recruiting 8 4 7 19 Equipment Procurement 24 7 20 Raw

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
HUNTSVILLE PLANT TASK LIST Task Number Task Name Duration (Weeks) Predecessor(s) 1 Huntsville Plant - Project (Project Level Task) 2 PLANNING PHASE (Summary) 3 Select Architect 2 none 4 6 none 5 Select Real Estate Consultant 2 none 6 Pre-Production Plan 2 none 7 Create Production Plan 4 6 8 Building Concept 2 6, 3 9 Building Design 6 8 10 Site Procurement 3 5, 8 11 Select General Contractor 2 8 12 3 5, 10, 11 13 PREPARATION PHASE (Summary) 14 Site Preparation 4 9, 10, 12 15 Building Construction
Background image of page 1
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: 24 9, 12, 14 16 Landscaping 3 15 17 PLANT READINESS PHASE (Summary) 18 Plant Personnel Recruiting 8 4, 7 19 Equipment Procurement 24 7 20 Raw Material Procurement 8 7 21 Equipment Installation 4 15, 18, 19 22 Product Distribution Plan 2 7 23 Truck Fleet Procurement 8 15, 22 24 Pre-Production Plan 4 18, 20, 21 25 PRODUCTION PHASE (Summary) 26 Production Start-Up 1 24 27 Distribution 1 23, 26...