BH0-010 ISEB ISEB Certified Tester Foundation Level (2010 Syllibus)
QUESTION: 112 The list below (a to e) describes one major task for each of the five main activities of thefundamental test process. Which option (A to D) places the tasks in the correct order, by time?a) Create bi-directional traceability between test basis and test cases. b) Check test logs against exit criteria. c) Define the objectives of testing. d) Check planned deliverables have been delivered. e) Comparing actual results with expected results. A. a, c, b, e, d B. c, a, d, e, b C. c, a, e, b, d D. d, a, c, b, e Answer: C QUESTION: 113 Given the following state transition diagram: Which of the test cases below will cover the following series of state transitions? SS S1 S2 S1 S2 ES A