Issues During Construction Chapter 3 180:305
Background image of page 1

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Acceptance Period/Withdrawal Low bidder must enter into contract Owner must provide written notice to  proceed within 60-90 days If no notice from owner, contractor can  withdraw bid after 60 day period.
Background image of page 2
Figure 3.1  (p. 48) Chronology of bid procedure.
Background image of page 3

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Change Order Written agreement to modify, add to, or  otherwise alter the work  Changes the contract documents  Must be within scope of original project  Price change may be involved with change  order  
Background image of page 4
Time Extension Unusual events cause a project delay Hurricane A change order is issued to extend project  completion date
Background image of page 5

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Table 3.1  (p. 49) Average Percent Extension by Extension Type
Background image of page 6
Reasons for Change Order Additions/Deletions to work Correct errors  in plans or specs  Change in method of construction   Change in contract time    Change  in order of work
Background image of page 7

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Types of Changes Directed  Change is requested by owner  Constructive  Change is requested by contractor Reasons:  Defective plans  Impossibility of performance Change in construction sequence or method  Major Source of Disputes  
Background image of page 8
Compensable/Noncompensable Delays A delay is compensable when the owner 
Background image of page 9

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full DocumentRight Arrow Icon
Image of page 10
This is the end of the preview. Sign up to access the rest of the document.

This note was uploaded on 01/09/2009 for the course CIVIL ENGI 180:305 taught by Professor Williams during the Fall '07 term at Rutgers.

Page1 / 27

305chap3 - Issues During Construction Chapter 3 180:305...

This preview shows document pages 1 - 10. Sign up to view the full document.

View Full Document Right Arrow Icon
Ask a homework question - tutors are online