ch7_project_mgt_2

Cost trade offs and risks must be considered such as

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: ts • The process of developing an approximation of the monetary resources needed to complete project activities. • Cost trade-offs and risks must be considered, such as make versus buy, buy versus lease, and the sharing of resources. • The accuracy of a project estimate will increase as the project progresses through project life cycle. Hence cost estimating is an iterative process. • This includes labor, materials, equipment, services, and facilities, as well as special categories such as inflation allowance or contingency costs. 47 7.1 Estimate Costs • Human Resource Plan: includes project staffing attributes, personnel rates, and related rewards/recognition. • Risk register: to consider risk mitigation costs. • _______________ Estimating: uses the values of parameters, such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity, from a previous, similar project as the basis for estimating the same parameter for a current project. • ________________ Estimating: uses a statistical relationship between historical data and other variables (e.g., square footage in construction) to calculate an estimate for activity parameters, such as cost, budget, and duration. • Three-Point Estimates: (1) most likely (cM), (2) optimistic (cO), and (3) pessimistic (cP). – cE = (cO + 4cM + cP) / 6 • Reserve analysis: include contingency reserves to account for cost uncertainty. May be a percentage of estimated cost or fixed number. 48 7.2 Determine Budget • The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. • Historical relationships: For analogous and parametric estimates, the cost and estimation accuracy can vary widely. The strength of historical relationship should be specified. • Funding Limit Reconciliation: A variance between the funding limits and the planned expenditures will sometimes necessitate the rescheduling of work to level out the rate of expenditures. 49 7.2 Determine Budget • Cost Performance Baseline: A time-phased __________________ __________ (BAC)...
View Full Document

This document was uploaded on 01/28/2014.

Ask a homework question - tutors are online