To post path office 1 invitation lead time 10 wedding

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: (12) – Address Invitations (4) – Inv. To Post PATH Office (1) – Invitation Lead Time (10) – Wedding (1) – length 31 days. Office PATH 7: Prepare Guest List (4) – Address Invitations (4) – Inv. To Past Office (1) – Invitation Lead PATH Time (10) – Wedding (1) – length 20 days. Time Some assumptions are in order: (1) we assume that we can start tomorrow (April 1), (2) everyone Some works 7 days a week. Path 1, 5 and 6 are all critical. Path 5 and 6 will have to be crashed to meet the wedding date of April 22. 2...