11 adjustedbyguthrie1974factors i cbm cpb fbm

Info iconThis preview shows page 1. Sign up to view the full content.

View Full Document Right Arrow Icon
This is the end of the preview. Sign up to access the rest of the document.

Unformatted text preview: rs I CBM CPb FBM Fd Fp Fm 1 Ib FBM = bare‐module factor Fd = equipment design factor Fp = pressure factor Fm = material factor 11 ChBE 4505/4525 Schork L7 Step 4 Obtain total bare‐module cost, CTBM by summing Bare‐module costs for all pieces of equipment Step 5 Use CTCI CTPI CWC 1.18(CTBM Csite Cbuildings Coffsite facilities ) CWC To estimate Total Permanent Investment And Total Capital Investment 12 ChBE 4505/4525 Schork L7 End of L7 13...
View Full Document

This note was uploaded on 04/10/2014 for the course CHBE 4525 taught by Professor Staff during the Spring '08 term at Georgia Institute of Technology.