Answer False Response See page 201 Level medium 18 When the work is routine

Answer false response see page 201 level medium 18

This preview shows page 4 - 7 out of 13 pages.

Answer: FalseResponse: See page 201Level: medium18. When the work is routine, fast-tracking rarely causes serious problems.Answer: TrueResponse: See page 201Level: medium19. Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.Answer: FalseResponse: See page 202Level: medium20. Resource loading refers to the amounts of specific resources that are scheduled for use on specific activities or projects at specific times.Answer: TrueResponse: See page 202Level: easy21. One limitation of MSP is that all resources must share the same availability calendar.Answer: FalseResponse: See page 202Level: medium
Background image
22. MSP allows the PM to create an individual availability calendar for each resource on the projectAnswer: TrueResponse: See page 202Level: medium23. A task’s duration is a function of both the amount of labor required to complete the task as well as the calendar time required to complete it.Answer: TrueResponse: See page 211Level: medium 24. A resource allocation decision may be intended to avoid a future problem rather than correct a current problem.Answer: TrueResponse: See page 214Level: medium25. In general, steady state demand for human resources is highly desirable.Answer: TrueResponse: See page 214Level: medium26. Pools of like resources from which labor can be added temporarily to projects tend to increase costs for the firm as a whole.Answer: FalseResponse: See page 214Level: medium
Background image
27. Pools of like workers are most useful when labor is subdivided into highly specialized subtasks.Answer: FalseResponse: See page 214Level: difficult28. Applying “line balancing” techniques to balance the capacity of a project typically yields significant benefits. Answer: FalseResponse: See page 216Level: medium29. A limitation associated with traditional approaches to project management is that the dependency between resources and tasks is often ignored.Answer: TrueResponse: See page 230Level: medium30. The as late as possible priority rule is considered the standard scheduling rule.Answer: FalseResponse: See page 217Level: mediumMultiple Choice
Background image
Image of page 7