SelectedAnswer:c.executingAnswers:a.initiatingb.closingc.executingd.planning
0 out of 1 pointsDuration relates to the time estimate, not the effort estimate.
Question 2
0 out of 1 pointsThe tasks in a WBS must be developed as a sequential list of steps.
Question 30 out of 1 pointsDuration estimates are provided as a ____ number, such as four weeks; as a range, such asthree to five weeks; or as a three-point estimate.
Question 41 out of 1 pointsAs more information becomes available and decisions are made related to project scope, theproject team should update the project scope statement.SelectedAnswer:TrueAnswers:TrueFalse
Question 51 out of 1 pointsAfter you determine the reason for a dependency between activities, you must determine thetype of dependency.
Question 61 out of 1 pointsWork that is not included in the scope statement should be performed as needed.
Question 71 out of 1 pointsThe contents of scope statements can vary.
Question 80 out of 1 points
Planning includes tasks related to each of the ____ project management knowledge areas.SelectedAnswer:b.fiveAnswers:a.fourb.fivec.tend.sixteen
Question 90 out of 1 pointsHow many of the ten project management knowledge areas include planning tasks?
Question 100 out of 1 pointsMost project teams use the most pessimistic time to estimate activity durations.
Answers:TrueFalseQuestion 111 out of 1 pointsThe critical path is the shortest path through the network diagram.
Question 121 out of 1 pointsThe main groupings for the work in a WBS chart are listed in the second tier of boxes, calledlevel ____.SelectedAnswer:c.2Answers:a.0b.1c.2d.3
Question 131 out of 1 points
It is poor practice to use more than one approach for creating a cost estimate.
Question 141 out of 1 pointsA _____________ is a deliverable-oriented grouping of the work involved in a project thatdefines the total scope of the project.
Question 150 out of 1 pointsWhat is the PERT weighted average based on an optimistic estimate of six days, a most likelyestimate of eight days, and a pessimistic time of sixteen days?
c.eightd.tenThursday, October 6, 2016 9:04:59 PM EDT
End of preview. Want to read all 23 pages?

Upload your study docs or become a

Course Hero member to access this document

Term
Spring
Professor
N/A
Tags
Project Management, project manager

Newly uploaded documents

Show More

Newly uploaded documents

Show More

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture