14.A Project Manager is using AOA to perform critical path analysis. The network diagram isrepresented as shown below. Which of the following represents the critical path?ActivityDuration in DaysDependent onA3noneC3noneB2D5E2noneF4G3D,FH1D,FI2B,GR0H,IACEa.ABIRb.CDHRc.CDGIRd.EFGIR
C.CDGIR represents the critical path. It is the longest path through the network with aduration of 13 days.15.For the following sequencediagram, what is the float of activity B?
16.For the following sequence diagram, what is the float of activity H?
Page 5© Copyright 2017, Simplilearn. All rights reserved.
17.According to Herzberg, which of these is not an example of hygiene factor?
18.According to Maslow's hierarchy of needs, which is the lowest level that must be metbefore other levels can be met?a.Esteemb.Physiologicalc.Sociald.SafetyB.Physiological factors appear at the lowest level of Maslow's hierarchy pyramid.
19.Which of these is not a project benefits measurement selection method?Internal Rate of Return, Weighted Scoring models, and Net Present Value are all part of
the Project Benefits Management plan. PMBOK® Guide, 6th edition, p. 420.Which of these is a not a constrained optimization project selection method?
21.Which of these is a process in the Scope Management knowledge area?
Page 6© Copyright 2017, Simplilearn. All rights reserved.
Page 7© Copyright 2017, Simplilearn. All rights reserved.C.Control Scope process is part of scope management knowledge area. PMBOK® Guide, 6thedition, p. 129

Upload your study docs or become a

Course Hero member to access this document

Upload your study docs or become a

Course Hero member to access this document

End of preview. Want to read all 16 pages?

Upload your study docs or become a

Course Hero member to access this document

Term
Fall
Professor
a.elrhman
Tags
Project Management, project manager

Newly uploaded documents

Show More

Newly uploaded documents

Show More

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture