Crashable tasks C F on critical path Secondly we crash F which costs 250day

Crashable tasks c f on critical path secondly we

This preview shows page 9 - 10 out of 10 pages.

Image of page 9
The following is information regarding a construction project. Fill in the blanks and answer the questions that follow (Hint: questions build on one another): Activity Predecessor Pessimistic Time Most Likely Time Optimistic Time Slack Mean Variance J - 15 10 8 0 10.5 K - 9 8 7 5.5 8 L J 10 6 5 1.5 6.5 M J 3 3 3 N K & M 9 5 1 0 5 O K & M 10 7 4 5.5 P L & N 10 8 3 0 7.5 What is the critical path? 1.361 0.111 0.694 0 3 0 1.778 7 1 1.361 What is the expected (mean) and variance of the duration of the critical path? What is the probability that the project will be completed in fewer than 30 days?
Image of page 10