activity can be shortened based on its predecessor. A need to level resources is a distracter.
[Crosswind Manual 6.3.5; PMBOK® Guide 6.3.2.3]
Schedule Practice Exam (30 Questions)7 of 151/29/2020, 10:23 AM
Question 15Correcttrack within resource constraints. Which of the following is most likely the project manager'sprimary concern?1.00 points out of1.00Question 16Correctquite experienced at. The client needs the estimate quickly. Which of the following types ofestimates is he likely to provide?1.00 points out of1.00The project manager is considering resource leveling the schedule to get the project back ontrack within resource constraints. Which of the following is most likely the project manager'sprimary concern?
The project manager is creating an estimate for a data warehouse. This is something he isquite experienced at. The client needs the estimate quickly. Which of the following types ofestimates is he likely to provide?
Schedule Practice Exam (30 Questions)8 of 151/29/2020, 10:23 AM
Question 17Correctnetwork). It is something that is new to the project manager and his team. They decide tocreate a bottom-up estimate. All the following are advantages of this type of estimateexcept?1.00 points out of1.00Question 18CorrectThe correct answer is: It takes a great amount of time to create1.00 points out of1.00The project manager is creating an estimate for building a company WAN (wide areanetwork). It is something that is new to the project manager and his team. They decide tocreate a bottom-up estimate. All the following are advantages of this type of estimateexcept?Select one:a. It provides team buy-in when they help create itb. There is a greater degree of accuracy because of the detail at which it was createdc. It provides supporting detail of the estimated. It takes a great amount of time to createAll the answers are characteristic of the bottom-up estimate. Taking a great amount of timeto create is not an advantage of the estimate. [Crosswind Manual 6.4.1; PMBOK® Guide
6.4.2]The correct answer is: It takes a great amount of time to create