Question 16CorrectThe project manager is working with the customer to gain formal acceptance ofthe project deliverables. The customer is saying that three of the deliverables arenot meeting project goals and are unusable in their present form. The teamdiscovers this was caused by an inconsistency between the requirements, scopestatement and WBS. Which process will the team use to align these documents?
1.00 points out of
1.00
Select one:a. Gather requirementsb. Validate scopec. Control scope d. Analyze scopeControl Scope is used to review, then approve or reject, project scope changerequests. A change request would be created to align the inconsistencies withthe requirements, scope statement, and WBS. Analyze Scope and GatherRequirements are distracters. Validate Scope helps validate that the projectcreated what it was to meant create. [Crosswind Manual 5.6; PMBOK® Guide5.6]The correct answer is: Control scope

1/24/20, 7
:
05 PM
Scope Practice Exam (30 Questions)
Page 14 of 24
Question 17CorrectThe project manager wants to better control her project. She is usingdecomposition after attending a project management class. Of the followingbreakdown structures and descriptions, which is correct?
1.00 points out of
1.00

1/24/20, 7
:
05 PM
Scope Practice Exam (30 Questions)
Page 15 of 24