Activities include: Confirm complete installation of all required parts Perform hydro test Perform pressure test Problem-solve all issues with gaskets, welds, & valves Perform system cleanout Caustic wash/surfactant to remove oil, grease, & other contaminants Detergent flush Acid wash to complete the cleaning process & remove elemental iron from stainless steel surfaces Visually inspect tanks & piping to verify that clean-in-place (CIP) systems are adequate Perform system passivation Chemical wash to protect cleaned stainless steel from chloride attack System sterility Initially, a system is sterilized by direct injection of low-pressure steam. Equipment, piping, and sterile barrier surface temperatures are checked and documented.
Image of page 23
24 When necessary, a sterility challenge is performed. The system is inoculated with sterile media, and bacteria growth is monitored for several days. If contamination occurs, the system is completely disassembled and inspected to identify the root cause. Sometimes, the system later shows evidence of contamination after a successful sterility challenge. AMG, Inc., can be called in to identify the source of contaminants and suggest actions that will prevent future contamination. What can cause repeated contamination of a previously sterilized production system? Examples include: Equipment design or maintenance Staff procedures or practices Stainless steel integrity Sterilizing equipment failure Clean-in-place equipment failure Building contaminants, such as airborne particulates & organisms Mechanical completion audits The audit includes such activities as: Confirm correct equipment installed Confirm correct installation procedure for each piece of equipment Check type & amount of lubrication Check rotation Electrical & instrumentation calibration & check-out Since many new processing plants install state-of-the-art control systems such as DeltaV™, commissioning and start-up include such activities as: Check hardware, including wiring, to ensure that each motor starts from the correct motor control center (MCC) Check software addressing to ensure each motor & instrument responds from the correct icon on the display Start all pieces of equipment Check power supply & functionality Check safety & software interlock sequences using o AMG, Inc., written documentation and/or o Client-written documentation reviewed by AMG, Inc. Perform system trial runs with water or sacrificial product Tune process control loops, such as temperature, pressure, flow Train operators Perform turn-over
Image of page 24
25 Start-up, Commissioning & Testing of Electrical Systems Introduction: Equipment readiness for a commercial service is proven by testing all its functions under different conditions. 'Do not believe, until it is proven' is the key to successful testing and satisfactory operation of electric systems. Equipment is finally proven when it is energized and tested on load during the start-up (first energisation).
Image of page 25
Image of page 26

You've reached the end of your free preview.

Want to read all 31 pages?

What students are saying

  • Left Quote Icon

    As a current student on this bumpy collegiate pathway, I stumbled upon Course Hero, where I can find study resources for nearly all my courses, get online help from tutors 24/7, and even share my old projects, papers, and lecture notes with other students.

    Student Picture

    Kiran Temple University Fox School of Business ‘17, Course Hero Intern

  • Left Quote Icon

    I cannot even describe how much Course Hero helped me this summer. It’s truly become something I can always rely on and help me. In the end, I was not only able to survive summer classes, but I was able to thrive thanks to Course Hero.

    Student Picture

    Dana University of Pennsylvania ‘17, Course Hero Intern

  • Left Quote Icon

    The ability to access any university’s resources through Course Hero proved invaluable in my case. I was behind on Tulane coursework and actually used UCLA’s materials to help me move forward and get everything together on time.

    Student Picture

    Jill Tulane University ‘16, Course Hero Intern

Stuck? We have tutors online 24/7 who can help you get unstuck.
A+ icon
Ask Expert Tutors You can ask You can ask You can ask (will expire )
Answers in as fast as 15 minutes