Question 21
0 out of 1 points
The WBS can be created in a number of forms except which of the following?
Question 22 0 out of 1 pointsWhich process involves verification and acceptance of all project deliverables, and hence supports the Close Project or Phase process?

Question 23 1 out of 1 pointsA project has gone out of control and the project manager is trying to bring it back under control. There have been a number of changes to the project scope, and some of the changes resulted in further changes such that the project cost spiraled and went out of schedule. This isknown as:
Response Feedback:
Good work
Question 24
1 out of 1 points
The most detailed level of the WBS is called the _______________.
Response Feedback:
Good work
Question 25 1 out of 1 pointsYou have been assigned a project where you are responsible for building a condo complex in a resort town. The project is expected to take two years to complete. During your WBS meeting you have decomposed many deliverables into work packages and schedule activities; however, there are some work packages that will be occurring a year from now, so you have elected not to decompose those deliverables and work packages at this time. This is an example of what tool and/or technique?

Response Feedback:
Good work
Question 26
0 out of 1 points
What is the logical sequence of the project scope management processes?


You've reached the end of your free preview.
Want to read all 25 pages?
- Fall '15
- Project Management, Correct Answer, project manager