Flag question Question text You are the Project Managers of XYZ consultants. The Project team members are from Finance and HR departments. The team members report to Finance and HR Managers respectively, and you have limited control over them. What type of organizational hierarchy does XYZ consultants follow? Select one:
Question 17 Correct Mark 1.00 out of 1.00 Flag question Question text Which of the following is not normally an element of the Project Charter? Select one: a. Work package descriptions. b. The product description or a reference to this document. c. The formal authorization to apply organizational resources to project activities. d. The business need that the project was undertaken to address. Feedback The correct answer is: Work package descriptions.