Partially correct Mark 400 out of 1200 Flag question Edit question Question

Partially correct mark 400 out of 1200 flag question

This preview shows page 13 - 17 out of 26 pages.

QUESTION Partially correctMark 4.00 out of 12.00 Flag questionEdit questionQuestion textComputation of Variances and Other Missing DataThe following data for Bernie Company pertain to the production of 500 units of Product X during December. Selected data items are omitted. Fill in the missing amounts.Direct materials (all materials purchased were used during period)Standard cost per unit: Answerpounds at $3.84 per pound (Round answer to one decimal place.)Total actual cost: Answer 6  
Direct materials (all materials purchased were used during period) pounds costing $8,510 Standard cost allowed for units produced: $8,640 Materials price variance: $Answer Answer Materials quantity variance: $216U Direct labor Standard cost: 2 hours at $10.50 Actual cost per hour: $10.90 Total actual cost: $Answer Labor rate variance: $Answer Answer Labor efficiency variance: $210 U Variable overhead Standard costs: Answer hours at $6.00 per direct labor hour 443.8 F 5450 10682 U 980
Direct materials (all materials purchased were used during period) Actual cost: $5,550 Variable overhead spending variance: $Answer Answer Variable overhead efficiency variance: $Answer Answer Feedback            pounds   ×  4.5) + ($216/$3.84)  pounds   ×  2,306.25)  F 0 F 0 U
            210    hours   ×  $10.90  =  $11,118    U  

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture