A it should include a method for controlling schedule

  • No School
  • AA 1
  • 28

This preview shows page 22 - 25 out of 28 pages.

A. It should include a method for controlling schedule B. It is better if it focuses on cost C. It is better if it concentrates on risk D. It should be created during the execution phase P.92 The characteristic of the precedence diagramming method that models construction projects differently than the arrow diagramming method is that it __________ A. uses arrows to signify logic in a network B. can be used to calculate the late start and late finish of all activities C. allows multiple relationship types to be associated with activities D. allows more than one critical path to be represented P.93 A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. A takes three weeks, B takes five weeks, and D takes 11 weeks. A and B must be completed before C can start. C requires six weeks to complete. B, C, and D must be
Image of page 22

Subscribe to view the full document.

General Revision-1 Magda El Talawy MD, PMP, PSP, CCP Page 23 completed before E can start. E requires two weeks. F takes four weeks and can start as soon as C is completed. E must be completed before G starts. G requires three weeks. F and G must be completed for the project to be completed. What is the critical path? A. A, C, F B. B, C, E and G C. D, E and G D. Both B, C, E, G and D, E, G. P.94 If the optimistic estimate for a task is 12 days and the pessimistic estimate is 18 days, what is the standard deviation of the task? A. 1 B. 1.3 C. 6 D. 3 P.95 Which of the following is true of activity duration estimating? A. Estimates should always include some indication of the range of possible results. B. It is more expensive. C. Historical data is too old to use in estimating. D. Critical paths help create original task estimates P.96 You have a project with four tasks as follows: Task 1 can start immediately and has an estimated duration of one. Task 2 can start after task 1 is completed and has an estimated duration of four. Task 3 can start after Task 2 is completed and has an estimated duration of five. Task 4 can start after Task 1 is completed and must be completed when Task 3 is completed. The estimate for Task 4 is ten. What is the shortest amount of time in which the project can be completed? A. 10 B. 9 C. 18
Image of page 23
General Revision-1 Magda El Talawy MD, PMP, PSP, CCP Page 24 D. 11 P.97 Which of the following does NOT need to be done if there is a major delay on a non- critical path activity? A. Investigate the delay B. Reevaluate which path is critical C. Change the project schedule D. Review slack time for the task P.98 If the optimistic estimate for a task is 12 days and the pessimistic estimate is 18 days, what is the most likely estimate? A. 15 days B. 13 days C. 16 days D. Unknown, the most likely estimate is a separate estimate P.99 The sponsor of the project you are managing asks you to compress the duration of the project. Which of the following is correct?
Image of page 24

Subscribe to view the full document.

Image of page 25

{[ snackBarMessage ]}

What students are saying

  • Left Quote Icon

    As a current student on this bumpy collegiate pathway, I stumbled upon Course Hero, where I can find study resources for nearly all my courses, get online help from tutors 24/7, and even share my old projects, papers, and lecture notes with other students.

    Student Picture

    Kiran Temple University Fox School of Business ‘17, Course Hero Intern

  • Left Quote Icon

    I cannot even describe how much Course Hero helped me this summer. It’s truly become something I can always rely on and help me. In the end, I was not only able to survive summer classes, but I was able to thrive thanks to Course Hero.

    Student Picture

    Dana University of Pennsylvania ‘17, Course Hero Intern

  • Left Quote Icon

    The ability to access any university’s resources through Course Hero proved invaluable in my case. I was behind on Tulane coursework and actually used UCLA’s materials to help me move forward and get everything together on time.

    Student Picture

    Jill Tulane University ‘16, Course Hero Intern