The hospital has 89 beds are these sufficient flow 28

This preview shows page 6 - 12 out of 21 pages.

The hospital has 89 beds are these sufficient? Flow rate = {28 + 28 + 28 + 28 + 28 + 0 + 0}[patients] / 7 [days] =(or 140 patients a week/7 days) = 20 [patients/ day] Flow time = 3.5 [days] (average of 3 and 4) WIP = 20 [patients/ day] * 3.5 [days] = 70 patients Do we have a problem? Since 70 people need 70 beds, 89 APPEARS to be ok. WIP = Flow rate * Flow time [Q] = [Q / T ] * [T ] Mgmt 361 Chapter 2 - Process Analysis 6
Image of page 6

Subscribe to view the full document.

Week 1 Week 2 Week 3 Day In Out Beds In Out Beds In Out Beds Sun Mon Tue Wed Thu Fri Sat 140 patients admitted Sunday through Thursday or 28 per day. Assume that we start with no patients in the hospital. 28 28 28 28 28 0 0 28 28 28 28 28 0 0 28 28 28 28 28 0 0 Only 89 beds, how are extra people accommodated? - 28 - 56 - 84 14 98 28 98 28 70 28 42 28 42 14 56 0 84 14 98 28 98 28 70 28 42 28 14 0 14 28 28 28 42 56 84 98 98 70 42 What we really need to understand is PEAK LOAD because you can’t ever have patients waiting for a bed More refined calculations for bed capacity: Chapter 2 - Process Analysis 7
Image of page 7
I n O ut P atients Week 2 Week 3 Day I O P I O P Sun 28 28 42 28 28 42 Mon 28 14 56 28 14 56 Tue 28 0 84 28 0 84 Wed 28 14 98 28 14 98 Thu 28 28 98 28 28 98 Fri 0 28 70 0 28 70 Sat 0 28 42 0 28 42 Flow rate = 140 [patients / week] / 7 [days/week] = 20 [patients / day] Flow time = 3.5 [days] WIP = average no. of patients = (42+56+84+98+98+70+42)/7 = 490 / 7 = 70 [patients] WIP = Flow rate * Flow time 70 [patients] = 20 [patients / day] * 3.5 [days] 3. Shouldice Hospital: Applying Little’s formula Chapter 2 - Process Analysis 8
Image of page 8

Subscribe to view the full document.

MGMT 361 Operations Management (OM) Ch II: Process Analysis - III Mgmt 361 Chapter 2 - Process Analysis 9
Image of page 9