Product structure for P1 and P2 are as follows: C4(1) & C6(2) = S3(1) = P2 C4(2) & C6(1) = S2(2) = P1 Component of raw material is M4. Two unit of M4 is needed to produce one unit of C4. The raw material used in component C 6 is M6. One unit of C6 is obtained from two units of M6. Lead times are as follows: P1: assembly lead time = 1 week P2: assembly lead time = 1 week S2: assembly lead time = 1 week S3: assembly lead time = 1 week Week number 6 7 8 9 10 Product P 1 50 100 Product P 2 70 80 25 etc, Period 1 2 3 4 5 6 7 Item: Raw Matl M 4 Gross Requirements Schedule Receipts 40 On Hand 50 90 Net Requirements Planned Order Release P2 S4 S3 C4 C6 C7 C2 C8 (1) (1) (2) (2) (2) (1) (1) Figure
Image of page 144

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
C4: manufacturing lead time = 2 weeks M4: ordering lead time = 2 weeks and inventory on hand is 100 C6: manufacturing lead time = 2weeks M6: ordering lead time = 2 weeks And inventory on hand is 50 How MRP works? (20 marks) 12. Discuss briefly the shop floor control in production management with the help of the diagram. (20 marks) 13. Discuss (1) Bar Code Technology (2) Bar Code Readers (3) Bar Code Printers (20 marks) 14. Explain (1) Data Acquisition System, (2) Multilevel Scanning in Automated Data Collection System. (20 marks) 15. Explain the term (i) outsourcing and (ii) Just-in-time production. (20 marks) 16. Explain the term (i) Point of use manufacture and (ii) Greater use of computers in manufacturing. (20 marks) 17. Explain briefly the Processing and Assembly function in manufacturing. (20 marks) 18. Explain the term “Material Handling“. (20 marks) 19. Discuss (1) Shorter product life cycle (2) Increased emphasis on quality and reliability (3) More customized products in manufacturing. (20 marks) 20. Discuss (1) New material (2) Growing use of Electrics (3) Pressure to reduce inventories in manufacturing. (20 marks) 21. Discuss the role of Information Processing and Database Management System in the future automated factory. (20 marks) 22. Discuss the concept of the Focused Factory. (20 marks)
Image of page 145
12 Computer Integrated Manufacturing IT 4036 for Second Semester Sample Answer & Question
Image of page 146

Info iconThis preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon