A project manager is about to start on a new project. Where would he find details about his authority level in the project? A. Organizational Process Assets B. The Project Charter C. The PMBOK D. The Scope statement Correct Answer: B Section: (none) Explanation Explanation/Reference: B - The project charter contains details of the assigned project manager and authority level. It provides the project manager the authority to apply organizational resources to project activities. [ PMBOK 5th edition , Page 71] [Project Integration Manag QUESTION 34 Which of the following is not true about the WBS? A. The project team must be involved in developing the WBS B. The WBS must represent all product and project work. C. WBS should focus on activities rather than deliverables D. WBS is usually represented in a hierarchical fashion Correct Answer: C Section: (none) Explanation Explanation/Reference: C - The WBS puts a greater focus on the deliverables than on actual activities. [ PMBOK 5th edition , Page 132] [Project Scope Management] Total Total QUESTION 35 Which of the following is accurate regarding the Estimate Activity Resources process? A. It produces project resource calendars as the output B. It determines dependencies that may require a lead or lag to define the relationship C. This process is coordinated independent of the Estimate Cost process D. It involves determining what and how many resources will be used
Image of page 72
Correct Answer: D Section: (none) Explanation Explanation/Reference: D - The Estimate Activity Resources process determines what and how many resources will be used. The resource calendars are inputs to this process and this process is closely coordinated with the Estimate Costs process. Activity leads and lags are not de QUESTION 36 In a project, Activity A has a duration of 4 days and begins on the morning of Monday the 4th. The successor Activity, B, has a Finish-to-Start (FS) relationship with A. The Finish-to-Start relationship has 2 days of lag, and Activity B has a duration of 3 days. If Saturday and Sunday are non working days, which of the following statements is true? A. Total elapsed days (completing both activities) is 7 days B. Activity B will be completed by the end of day on Thursday, 14th C. Activity B will be completed by the end of day on Friday, 15th. D. Activity B will be completed by the end of day on Tuesday, 12th Correct Answer: B Section: (none) Explanation Explanation/Reference: B - Activity A has a duration of 4 days and completes by end of the day on Thursday, 7th. There is a 2 day lag and since Saturday and Sunday are non-working, Activity B can begin only on Tuesday, 12th. Activity B has a duration of 3 days and completes by QUESTION 37 What is the BEST way to make an accurate forecasting of ETC? A. EAC - AC B. BAC – EV C. Manual forecasting of cost of the remaining work. D. (BAC – EV)/CPI Correct Answer: C Section: (none) Explanation Explanation/Reference:
Image of page 73
C - Manual forecasting of costs for remaining work is generally the best means of generating an accurate forecast. [ PMBOK 5th edition , Page 220] [Project Cost Management] Total Total QUESTION 38 Which of the following is not a valid instance of Risk Transference?
Image of page 74
Image of page 75

You've reached the end of your free preview.

Want to read all 433 pages?

  • Fall '16
  • Mr. Ryan Cooney
  • Project Management, Project risk management, Correct Answer, project manager

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture