a.Falseb.True23.What enhances the transparency of an increment? (Choose the best answer.)a.Doing all work needed to meet the definition of "Done"
b.Reporting Sprint progress to the stakeholders dailyc.Keeping track of and estimating all undone work to be completed in aseparate Sprint.d.Updating Sprint tasks properly in the electronic tracking tool.24.A Development Team is required to deliver a done increment by the end of a Sprint.Select two statements that explain what “done” means. (Choose two.)a.All work the Development Team is willing to do.b.Ready for integration.c.No work left from the definition of "Done".d.Whatever the Product Owner defines as quality.e.All work to create software that is ready to be released to end users25.Which two statements are correct about the Definition of Done?a. It helps the Product Owner measure the progress of the Sprint work.b. There can be more than one Definition of Done when multiple teams areworking on the same project.c. Used by the developers to forecast how many items they can pick for the Sprint.d. It's defined by the Scrum Master.26.The Definition of Ready may be adjusted and improved during the project.a.Falseb.True27.Who creates the definition of "Done"?a.The development organization (or Development Team if none isavailable from the development organization)b.TheScrum Master as he/she is responsible for the Development Team'sproductivityc.The Scrum Team, in a collaborative effort where the result is the commondenominator of all members' definitionsd.TheProduct Owner as he/she is responsible for the product's success
13.Charts / Cone of Uncertainty / Technical Debt1.What does a trend line through a release burn-down chart indicate? / If burndowncharts are used to visualize progress, what does a trend line through a releaseburndown chart indicate? (Choose the best answer.)a. The budgeted cost of the projectb. When the project will likely finish, if the team develops with a speed equal to thelast Sprintc. When the remaining work will likely be completed if nothing changes in theProduct Backlog or the Development Teamd. When the remaining work is supposed to be finished2.Drawing a trend line through a release burndown chart indicates?a. When the work remaining will likely be completed if nothing changes on thebacklog or Development Team.b. When all Sprint Backlog work will be completed and the Scrum Team will bereleased for other workc. Cost of the project.d. When the project will be over if the Product Owner removes work that is equal ineffort to any new work that is added3.Sprint burndown charts are an efficient tracking tool because they showa. How much effort has gone into a Sprintb. How many Product Backlog items remainc. Estimated work remaining for the Sprintd. How many hours have been worked by each Development Team member4.What are some consequences if a Development Team does not have a consistentdefinition of done from Sprint to Sprint?

Upload your study docs or become a

Course Hero member to access this document

Upload your study docs or become a

Course Hero member to access this document

End of preview. Want to read all 81 pages?

Upload your study docs or become a

Course Hero member to access this document

Term
Fall
Professor
NoProfessor
Tags

Newly uploaded documents

Show More

Newly uploaded documents

Show More

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture