Decisions Variables Objective Function Subject To1.2.
t1; be the green light time for H1t2; be the green light time for H2Number of cars arriving per second at h1= 500/3600Number of cars arriving per second at h2= 600/3600Number of cars arriving per second at h1= 400/3600t1 + t2 + t3 +3*10 <=132t1>=25 , t2>=25, t3>=25t3; be the green light time for H3max Z = 3*(500/3600)*t1 + 4*(600/3600)*t2 + 5*(400/3600)*t3
H1H2H3Yellow Light 101010Green Light255225Profit10.416667 34.667 13.889Total Profit58.972222Cycle Time 132
Sensivity Report 5There is an increase in the amount of shadow price.