Advise the development team to:
A. use power point slides with screenshots.
B. create a script and practice the playback.
C. postpone the playback if a technical problem is found.
15

D. warn stakeholders with possible technical problems in advance.
Answer:
B
QUESTION:
33
The BPM validation process is the first time BPM project for the development
team. At the project launch meeting, the functional requirements for the project are
requested by the developers and administrator. The program manager reminds the
team that functional requirementsare typically documented during a specific phase
in the BPM life cycle. When are the functional requirements for the process
documented?
A. Process discovery
B. Process simulation
C. Process optimization
D. Process identification
Answer:
A
QUESTION:
34
The BPM program manager is scheduling Playback 1 for a process application for
organizing events. Which of the following parties can be absent during Playback 1?
A. Process Owner
B. BPM Developer
C. Event Organizer
D. System Architect
Answer:
D
QUESTION:
35
The BPM analyst, Process Owner and BPM program manager have created a list of
user stories with point estimates. What do user story points measure?