Advise the development team to: A. use power point slides with screenshots. B. create a script and practice the playback. C. postpone the playback if a technical problem is found. 15
Image of page 2
D. warn stakeholders with possible technical problems in advance. Answer: B QUESTION: 33 The BPM validation process is the first time BPM project for the development team. At the project launch meeting, the functional requirements for the project are requested by the developers and administrator. The program manager reminds the team that functional requirementsare typically documented during a specific phase in the BPM life cycle. When are the functional requirements for the process documented? A. Process discovery B. Process simulation C. Process optimization D. Process identification Answer: A QUESTION: 34 The BPM program manager is scheduling Playback 1 for a process application for organizing events. Which of the following parties can be absent during Playback 1? A. Process Owner B. BPM Developer C. Event Organizer D. System Architect Answer: D QUESTION: 35 The BPM analyst, Process Owner and BPM program manager have created a list of user stories with point estimates. What do user story points measure?
Image of page 3
Image of page 4

You've reached the end of your free preview.

Want to read all 6 pages?

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture