Score 0 of possible 1 point a gantt chart would be

This preview shows page 6 - 7 out of 7 pages.

Question 9 of 10 Score: 0 (of possible1 A Gantt Chart would be most useful for which aspect of improving marketing implementation?point)A.Scheduling tasksB.Communicating goalsC.Rewarding successD.Avoiding "paralysis by analysis"E.Having a product championAnswer Key: AA) A Gantt Chart is a graphical representation of a program schedule. It is a tool designed to helpimprove scheduling tasks. B) The Gantt Chart shows what needs to be done and by when, so it may indirectly communicatesgoals. However, the chart does not really explain the overall goals or how they are to beaccomplished. C) A Gantt Chart is not useful for rewarding tasks. D) A Gantt Chart is helpful for showing what needs to be done and by when. However, a Gantt Chart
FeedbackText page 591