3. Refer to Figure 4.9. What activities must be accomplished before “Input Response Data” can start? What activities can start after “Review Comments & Finalize Questionnaire” has finished? List two activities that can be done concurrently.“Mail Questionnaire & Get Responses” and “Test Software” must be done before “Input Response Data” can start. “Prepare Mailing Labels,” “Print Questionnaire,” “Develop Data Analysis Software,” and “Develop Software Test Data” can start after “Review Comments & Finalize Questionnaire” has been completed. Any of the four activities listed above that can start after “Review Comments & Finalize Questionnaire” has been completed. 4. Using MS Project or Word, draw a network diagram that represents the following IS development task list. Use both the activity-in-the-box and the activity-on-the-arrow formats.
Activity Immediate Predecessor1. Problem Definition2. Study Current System13. Define User Requirements14. Logical System Design35. Physical System Design26. System Development4, 57. System Testing68. Convert Database4, 59. System Conversion7, 8756219834

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture

  • Left Quote Icon

    Student Picture