P a g e|16ABC Co. collects the billing, net of 10% retention by the customer to be used torectify any unsatisfactory work determined at the completion of the contract.How much is the cost of construction that is recognized as expense in 20x1?-
Get answer to your question and much more
34.ABC Co. started work on two separate projects during 20x1. Information onthese projects is shown below:ProjectContractpriceCosts incurredEstimated coststo completeProgressbillingsA9,000,0004,000,0002,000,0005,000,000B8,000,0005,000,000-8,000,000How much is the total balance of the “construction in progress” accounts as ofDecember 31, 20x1 under zero-profit method?
Get answer to your question and much more
35.PFRS 15 requires how many steps in recognizing revenue from contracts withcustomers?
Get answer to your question and much more