Earliest time an activity can start es maximum ef of

Info icon This preview shows pages 12–21. Sign up to view the full content.

earliest time an activity can start ES = maximum EF of immediate predecessors Earliest finish time (EF) earliest time an activity can finish EF= ES + t 12
Image of page 12

Info icon This preview has intentionally blurred sections. Sign up to view the full version.

CPM Calculation Latest Start Time (LS) Latest time an activity can start without delaying critical path time LS= LF - t Latest finish time (LF) latest time an activity can be completed without delaying critical path time LF = minimum LS of immediate successors 13
Image of page 13
CPM example 14 a, 6 a, 6 f, 15 f, 15 b, 8 b, 8 c, 5 c, 5 e, 9 e, 9 d, 13 d, 13 g, 17 g, 17 h, 9 h, 9 i, 6 i, 6 j, 12 j, 12 Activity Duration
Image of page 14

Info icon This preview has intentionally blurred sections. Sign up to view the full version.

CPM example 15 a, 6 a, 6 f, 15 f, 15 b, 8 b, 8 c, 5 c, 5 e, 9 e, 9 d, 13 d, 13 g, 17 g, 17 h, 9 h, 9 i, 6 i, 6 j, 12 j, 12 0 6 0 8 0 5 EST EFT
Image of page 15
CPM example 16 a, 6 a, 6 f, 15 f, 15 b, 8 b, 8 c, 5 c, 5 e, 9 e, 9 d, 13 d, 13 g, 17 g, 17 h, 9 h, 9 i, 6 i, 6 j, 12 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 Project’s EF = 33 EST EFT max
Image of page 16

Info icon This preview has intentionally blurred sections. Sign up to view the full version.

CPM example 17 a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 21 33 27 33 24 33 Project’s EF = 33 LFT LST
Image of page 17
CPM example 18 a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 3 9 0 8 7 12 12 21 21 33 27 33 8 21 10 27 24 33 9 24 3 4 3 3 4 0 0 7 7 0 min
Image of page 18

Info icon This preview has intentionally blurred sections. Sign up to view the full version.

CPM example 19 a, 6 f, 15 b, 8 c, 5 e, 9 d, 13 g, 17 h, 9 i, 6 j, 12 0 6 0 8 0 5 5 14 8 21 21 33 6 23 21 30 23 29 6 21 3 9 0 8 7 12 12 21 21 33 27 33 8 21 10 27 24 33 9 24 3 4 3 3 4 0 0 7 7 0
Image of page 19
Slack = LS – ES = LF – EF Slack is the length of time an activity can be delayed without affecting the completi on date for the entire project. For example , slack for C = LS – ES = 8 – 5 = 3 weeks or LF – EF = 12 – 9 = 3 weeks .
Image of page 20

Info icon This preview has intentionally blurred sections. Sign up to view the full version.

Image of page 21
This is the end of the preview. Sign up to access the rest of the document.

{[ snackBarMessage ]}

What students are saying

  • Left Quote Icon

    As a current student on this bumpy collegiate pathway, I stumbled upon Course Hero, where I can find study resources for nearly all my courses, get online help from tutors 24/7, and even share my old projects, papers, and lecture notes with other students.

    Student Picture

    Kiran Temple University Fox School of Business ‘17, Course Hero Intern

  • Left Quote Icon

    I cannot even describe how much Course Hero helped me this summer. It’s truly become something I can always rely on and help me. In the end, I was not only able to survive summer classes, but I was able to thrive thanks to Course Hero.

    Student Picture

    Dana University of Pennsylvania ‘17, Course Hero Intern

  • Left Quote Icon

    The ability to access any university’s resources through Course Hero proved invaluable in my case. I was behind on Tulane coursework and actually used UCLA’s materials to help me move forward and get everything together on time.

    Student Picture

    Jill Tulane University ‘16, Course Hero Intern