Question: 22Which estimate is given more weight in the PERT estimate formula?(a) Optimistic
(b) Pessimistic(c) Most Likely(d) None of the aboveExplanation:In the PERT estimate formula, the Most Likely estimate is given more weight. ThePERT estimate formula is = (Optimistic + 4*Most-Likely + Pessimistic)/6
Reference:The PMBOK Guide 6th Edition, Page: 245Question: 23What does the Variance at Completion show?
Reference:The PMBOK Guide 6th Edition, Page: 262Question: 24You are developing the project charter, with management, for a new project. You are going to be the project manager. Who will sign the project charter?
Reference:The PMBOK Guide 6th Edition, Page: 75Question: 25Your management has asked you to provide them with the rough order estimate for a project on an urgent basis. In this case, which of the following techniques will you use?
Reference:The PMBOK Guide 6th Edition, Page: 200
Question: 26Your project is late and to bring it back on track you are adding extra resources to some activitiesand giving overtime to your team members. This is an example of:(a) Critical Chain(b) Fast Tracking(c) Crashing(d) Resource Leveling
Explanation:You are adding extra resources to your activities, which is an example of Crashing.Reference:The PMBOK Guide 6th Edition, Page: 215Question: 27Which document authorizes the existence of the project?