On 19 april the defendant paid another 150 work was

Info icon This preview shows pages 11–21. Sign up to view the full content.

View Full Document Right Arrow Icon
On 19 April, the defendant paid another £150. Work was completed on 25 August. On 28 August, the plaintiff asked the defendant to pay the balance. The defendant complained about poor workmanship for a book shelf and wardrobe and paid the plaintiff £100 but refused to pay the balance. The plaintiff then sued the defendant. 11 a. DISCHARGE OF CONTRACTS
Image of page 11

Info icon This preview has intentionally blurred sections. Sign up to view the full version.

View Full Document Right Arrow Icon
Held : On the facts the contract had been substantially performed even though defects would cost £55 to correct. Thus the plaintiff was entitled to recover the contractually agreed price of £750 minus £55. 12 a. DISCHARGE OF CONTRACTS