5) Which schedule duration estimating method uses statistical relationships determined from historical data to calculate the estimate for certain tasks? [4.3.4 - Using a task duration estimating calculation, select the correct estimating technique.] Parametric Estimate Analogous Estimate Three-Point Estimate Single-Point Estimate Page 2 of 5 DAU
6) The summary schedule is generally associated with levels 1-3 of the Work Breakdown Structure (WBS), whereas the intermediate schedule is generally associated with which WBS levels? [4.3.5 - Identify the differences in schedules produced, as an output of constructing program schedules.]
7) How are schedules in a schedule change management system similar to project elements under configuration management (CM)? [4.3.6 - Identify the key factors of a schedule change management system, as part of monitoring and control of program schedules.]
8) Which of the following are characteristics of the use of Agile Project Management in scheduling? (Select two that apply.) [4.3.7 - Explain the effects of agile project management on scheduling.] [Remediation Accessed :N]
6/13/2018
Plan for new and usable functionalities should a project’s requirements stay unchanged . Prepare to use traditional scheduling tools in novel ways in order to adapt to agile projects. 9) Subsequent to the development of the Gantt chart, planners and managers used a similar approach to depict information about significant project events focused on specific points in time. Which schedule type is being described? [4.4.1 - Identify the types of schedules commonly used in program management.] Milestone chart Network diagram Resource schedule Internal schedule