Week 1-3: pouring of foundations. Foundation inspection to be conducted to guarantee that the right materials have been used, the thickness and quality of the materials to be used are also inspected alongside the equipment to be used. Week 4-5: Framing of the floors, roof and walls. Incase the building has more than one storey, then all the floors and walls in each storey should be done simultaneously. The roof will be shingled and sheathed after the walls and the floors have been framed. Inspection will be conducted after framing and flooring is done to check on safety and quality. Exterior finishes and fisher boards to be installed immediately the inspector approves the work done.
Image of page 4

Subscribe to view the full document.

PROJECT PROPOSAL 5 Week 6-8: Electrical, plumbing and installation of the other systems. inspection will be done at a later time to ensure quality, safety and layout framework are installed as per the requirements made. Drywall and insulations are to be installed immediately the inspectors have approved the systems. Week 9-11: Completion of the interior designs including the paintings, setup of cabinets, finishing on floors and minor molding and trimmings. Week 12-14: Finishing through the installation of counter tops, appliances switches and inlet and outlet piping. Conclusion of plumbing and electrical works. Completion of any interior design and turning on of all the installed systems. If any issues are realized, then they are fixed prior to the approval of the entire project. a close out is normally initiated the moment everything is approved. Estimate the project’s overall cost and key staffing and non-staffing resources needed The renovation project is estimated to take one hundred and twenty dollars. Key staffing requirements involves the members who will be responsible in ensuring the demolition is undertaken, painting is completed as required and flooring is completed. Project assistants will provide help when it comes to coordination of the project team members. The role of the manager remains overseeing the entire project as a whole.
Image of page 5
Image of page 6

What students are saying

  • Left Quote Icon

    As a current student on this bumpy collegiate pathway, I stumbled upon Course Hero, where I can find study resources for nearly all my courses, get online help from tutors 24/7, and even share my old projects, papers, and lecture notes with other students.

    Student Picture

    Kiran Temple University Fox School of Business ‘17, Course Hero Intern

  • Left Quote Icon

    I cannot even describe how much Course Hero helped me this summer. It’s truly become something I can always rely on and help me. In the end, I was not only able to survive summer classes, but I was able to thrive thanks to Course Hero.

    Student Picture

    Dana University of Pennsylvania ‘17, Course Hero Intern

  • Left Quote Icon

    The ability to access any university’s resources through Course Hero proved invaluable in my case. I was behind on Tulane coursework and actually used UCLA’s materials to help me move forward and get everything together on time.

    Student Picture

    Jill Tulane University ‘16, Course Hero Intern

Ask Expert Tutors You can ask You can ask ( soon) You can ask (will expire )
Answers in as fast as 15 minutes