Blossom Construction Company had a contract starting April 2018, to construct a $23800000 building that is expected to be completed in September...

Blossom Construction Company had a contract starting April 2018, to construct a $23800000 building that is expected to be completed in September 2020, at an estimated cost of $21800000. At the end of 2018, the costs to date were $9592000 and the estimated total costs to complete had not changed. The progress billings during 2018 were $460000 and the cash collected during 2018 was 3180000. Blossom uses the percentage-of-completion method.


At December 31, 2018 Blossom would report Construction in Process in the amount of:





$9132000.


$880000.


$10472000.


$9592000.

Top Answer

Total Contract Price 23800000 Total estimated costs... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online