Crane Construction Co. has consistently used the percentage-of-completion method of recognizing revenue.

Crane Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2018, Crane entered into a fixed-price contract to construct an office building for $27000000. Information relating to the contract is as follows:


          At December 31          

2018 2019

Percentage of completion 10% 40%

Estimated total cost at completion $20000000 $21400000

Gross profit recognized (cumulative) 1380000 3310000



Contract costs incurred during 2019 were


$5250000.


$6560000.


$8190000.


$8560000.

Top Answer

The best way to approach your question... View the full answer

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online