Ivanhoe Construction Co. uses the percentage-of-completion method. In 2018, Ivanhoe began work on a contract for $21000000; it was completed in 2019....

Ivanhoe Construction Co. uses the percentage-of-completion method. In 2018, Ivanhoe began work on a contract for $21000000; it was completed in 2019. The following cost data pertain to this contract:


 Year Ended December 31

  2018 2019

Cost incurred during the year $6600000 $5500000

Estimated costs to complete at the end of year 5100000 —



The amount of gross profit to be recognized on the income statement for the year ended December 31, 2019 is


$3653846.


$3800000.


$4053846.


$8900000.

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question