Hawk Construction, Inc. had a 3-year project whose contract price is $8,000,000. Construction activities are

summarized in the table below.

           

                                   12/31/17         12/31/18         12/31/19

Costs to date                                       2,000,000       5,000,000       9,000,000

Additional costs to complete             3,000,000       4,000,000        -0-

Progress billings to date                     2,500,000       5,500,000       8,000,000

Cash collected to date                        2,300,000       5,400,000       8,000,000

 

Instructions: Prepare any necessary journal entries for the above project in 2017, 2018, & 2019 using 1) the percentage of completion method, 2) the completed contract method.

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask Expert Tutors You can ask You can ask ( soon) You can ask (will expire )
Answers in as fast as 15 minutes