On January 2, 2010, Indian River Groves began construction of a new citrus processing plant. The automated plant was finished and ready for use on...

On January 2, 2010, Indian River Groves began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2011. Expenditures for the construction were as follows:
January 2, 2010 $200,000
September 1, 2010 600,000
December 31, 2010 600,000
March 31, 2011 600,000
September 30, 2011 400,000


Indian River Groves borrowed $1,100,000 on a construction loan at 12% interest on January 2, 2010. This loan was outstanding during the construction period. The company also had $4,000,000 in 9% bonds outstanding in 2010 and 2011.
What were the weighted-average accumulated expenditures for 2011 by the end of the construction period?

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question