Reese Construction Corporation contracted to construct a building for $1,500,000. Construction began in 2007 and was completed in 2008. Data relating...

Reese Construction Corporation contracted to construct a building for $1,500,000. Construction began in 2007 and was completed in 2008. Data relating to the contract are summarized below:
                                           Year Ended
                                             Dec. 31
                                      2007             2008
     Costs incurred                 $600,000         $450,000
     Estimated cost to complete     $400,000            -0-
Reese uses the percentage-of-completion method as the basis for income recognition. For the years ended December 31, 2007, and 2008, respectively, Reese should report gross profit of
A. $270,000 and $180,000.
B. $300,000 and $150,000.
C. $900,000 and $600,000.
D. $0 and $450,000.

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question