Percentage-of-completion method. Dalton Construction Co. contracted to build a bridge for $5,000,000. Construction began in 2010 and was completed...

1. Percentage-of-completion method.
Dalton Construction Co. contracted to build a bridge for $5,000,000. Construction began in 2010 and was completed in 2011. Data relating to the construction are:
2010 2011
Costs incurred $1,650,000 $1,375,000
Estimated costs to complete 1,350,000 —

Dalton uses the percentage-of-completion method.

Instructions
(a) How much revenue should be reported for 2010? Show your computation.
(b) Make the entry to record progress billings of $1,650,000 during 2010.
(c) Make the entry to record the revenue and gross profit for 2010.
(d) How much gross profit should be reported for 2011? Show your computation.

Top Answer

Here is the explanation for... View the full answer

Solution of CH010510_497754_ACC.xls

Question:. Percentage-of-completion method.
Dalton Construction Co. contracted to build a bridge for $5,000,000. Construction began in 2010 and was completed in 2011. Data relating to the...

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online