Benson Company, which uses a standard cost system, budgeted $600,000 of fixed overhead when 40,000 machine hours were anticipated. Other data for the...

Benson Company, which uses a standard cost system, budgeted $600,000 of fixed overhead when 40,000 machine hours were anticipated. Other data for the period were:
Actual units produced: 10,000
Standard production time per unit: 3.9 machine hours
Fixed overhead incurred: $620,000
Actual machine hours worked: 42,000
Benson's fixed-overhead budget variance is:
A. $10,000 Favorable
B. $15,000 Favorable
C. $20,000 Favorable
D. $15,000 Unfavorable
E. $20,000 Unfavorable

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question