In 2011, Fayette Engineering entered into an agreement to construct an office building at a contract price of $5,100,000. Construction data were as...

16. In 2011, Fayette Engineering entered into an agreement to construct an office building at a contract price of $5,100,000. Construction data were as follows:
               2011 2012          2013
Construction costs
  incurred $  750,000 $2,700,000 $  630,000
Estimated costs to
  complete 3,000,000    862,500        --
Progress billings    570,000 3,600,000   930,000
Collections from client   450,000 3,300,000 1,350,000
Prepare the necessary entries for 2011, assuming the firm uses the percentage of completion method:
17.   (4 points) Kamus Medical Center uses the cost recovery method of accounting for recognizing revenue. The following information is available:
                   2011 2012      2013  
Sales ................... $45,000 $60,000 $85,000
Gross profit percentage . 37% 41% 40%
Cash collections:
   2011 ................. $24,000 $19,000 $ 2,000
   2012 ................. 40,000 17,000
   2013 ................. 53,000
Determine the amount of gross profit to be recognized for 2011 and 2012

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question