On March 15, 2010, Frankel Construction contracted to build a shopping center at a contract price of $120 million. The schedule of expected (equals...

On March 15, 2010, Frankel Construction contracted to build a shopping center at a contract price of $120 million. The schedule of expected (equals actual) cash collections and contract costs follows:

Year Cash Collections Cost Incurred

2010 $30 million $15 million

2011 50 million 40 million

2012 40 million 30 million

Total $120 million $85 million



a. Calculate the amount of revenue, expense, and income for each of the three years 2010 through 2012 using (1) the percentage-of-completion method, (2) the completed contract method, and (3) the installment method.

b. Discuss which method you believe provides the best measure of the construction company's performance under this contract.
Sign up to view the entire interaction

Top Answer

Apologies. Dint get saved. Had done... View the full answer

8422084.xls

(Value in million $) Contract value 2010 2011 2012 120 Cash collected incurred Cost 30 15 50 40 40 30 (1) Percentage of completion method 2010 2011 % Complete 17.65% 64.71% Revenue Expense Income...

Sign up to view the full answer

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question
Ask a homework question - tutors are online