16-28 variable cost variances The following data reflect the current month's activity for Sills, Inc.

16-28 variable cost variances
The following data reflect the current month’s activity for Sills, Inc.:
Actual total direct labor $546,000
Actual hours worked 26,000
Standard labor-hours allowed for actual output (flexible budget) 27,000
Direct labor price variance $19,500U
Actual variable overhead $132,600
Standard variable overhead rate per standard direct labor-hour $5.25

Variable overhead is applied based on standard direct labor-hours allowed.
Required
Compute the labor and variable overhead price and efficiency variances.

16.32 fixed cost variances
Information on Carney Company’s fixed overhead costs follows:
Overhead applied $360,000
Actual overhead 385,500
Budgeted overhead 369,000
Required
What are the fixed overhead price and production volume variances?

Recently Asked Questions

Why Join Course Hero?

Course Hero has all the homework and study help you need to succeed! We’ve got course-specific notes, study guides, and practice tests along with expert tutors.

-

Educational Resources
  • -

    Study Documents

    Find the best study resources around, tagged to your specific courses. Share your own to gain free Course Hero access.

    Browse Documents
  • -

    Question & Answers

    Get one-on-one homework help from our expert tutors—available online 24/7. Ask your own questions or browse existing Q&A threads. Satisfaction guaranteed!

    Ask a Question